Laboratory fitout to a newly constructed base building
Fitout and modifications to an existing medical research space
Key Statistics
Builder
Arete
Consultant
Waterman
Architect
STH
Contract Value
$1.5-2M
Project Completion
2024
Project Scope
Supply, install and commission:
- Dedicated 4 pipe heat pump thermal plant and associated water system serving the PC2 lab.
- FCUs with humidity control serving the PC2 lab under negative pressure
- Ventilation systems for amenity and safety.
- Medical and laboratory gases
- Dedicated fitout BMS with integration into the base building system